Build Advice
BUILD ADVICE RESPONSE — Example BA-000033
Progress Claim & Variation Review · Lucy Parker
Your Question / Issue
You have requested a review of Progress Claim 04 totalling NZ$31,800.00 incl. GST for your residential renovation at 42 Sample Lane, Auckland. The claim comprises NZ$25,000.00 incl. GST for Stage 04 (roof covering and associated framing works) and NZ$6,800.00 incl. GST for proposed Variation V-03 (stormwater drainage pipe replacement). You are seeking clarity on the contractual scope boundaries, the requirement for written variation sign-off, the necessary supporting documentation, and the completion status of the milestone stage.
Build Advice — what we found and what it means
Based on the documentation supplied, our assessment covers two distinct items within Progress Claim 04: proposed Variation V-03 for stormwater drainage replacement, and the milestone claim for Stage 04 roof and framing works.
Recommended Next Steps
- Request written confirmation from the contractor clarifying whether the 18 metres of stormwater drainage pipe has physically been excavated and installed, or if the claim is based entirely on estimate ES-03 and supplier quote SQ-18 before work took place.
- Request solid diagnostic and photographic proof of the drainage defect, including CCTV footage or logs showing the crushed or blocked pipe, photographs before removal, and as-built photos of the replacement installation.